​Project Overview:  ES-0541

New road construction extending Horton Road west as a secondary urban arterial with sidewalks, bike lanes, illumination and turn lanes.  This will provide an east-west connector from Meridian to Northwest Drive.

Federal funding of $1,000,000 from the City Street Fund.

Status - October 2019

Accomplishments:  Securing the Federal funding for this project. Survey existing alignment and wetlands.

Next Milestone:  Complete 30% design.

Project Details

  • Status- Design
  • Contract Awarded-
  • Contract Amount-
  • Contractor-
  • Vicinity Map