Squalicum Creek Park Phase 4 Development

Description

Squalicum Creek Park Phase 4 includes a new ball field/multi-purpose sport field, related backstop, dug outs and paving. The project also includes a low-impact infiltration basin.

Status & Project Schedule

Active. RW Droll Landscape Architect, PS, has been hired to design the new sport facility.

Design Phase               now – end of March 2020

Permits                         now – mid April 2020

Bid Phase                     mid April – mid May 2020

Construction Phase      mid June – mid October 2020

Phase 4 Budget & Funding Source

• Budget: $1.25 million

• Funding Source: State Youth Athletic Facility (YAF) Grant, Greenway 3 Levy and Park Impact Fees

Contractor & Consultants

City's Project Manager: Jonathan Schilk, RLA

 

Design Consultants:

RW Droll Landscape Architect, PS

Reichhardt & Ebe Engineering, Inc.

GeoEngineers, Inc.

Stantec, Inc.

 

Contractor: TBD

Reference

Master Plan (PDF)

Squalicum Park Phase 4 Fact Sheet (PDF)

Concept Plan

Affected Neighborhoods

    Birchwood; Columbia

Participating Departments

    Parks and Recreation