Watermain Replacement Program (2016)

​Project Overview: EW-0230

The 2016 Water Main Replacement project is part of an annual program to replace aging water mains that are at the end of their lifecycle and require upgrades to better provide reliable water service. This project will replace water mains on West Holly Street from Central Avenue to Broadway, and on E Street from West Holly Street to Dupont Street. Construction is currently scheduled for November 2016 to April 2017.

Status - September 2017

Accomplishments:  Project Complete - Warranty Period

 Next Milestone:  

Project Details

  • Status - Construction Complete
  • Contract Awarded -   October 24, 2016
  • Contract Amount -  $1,877,297.56
  • Contractor -  Ram Construction General Contractors
  • Completion Date:  August 25, 2017
  • Final Contract Amount:  $2,474,838.38
  • Vicinity Map

Affected Neighborhoods

    City Center; Lettered Streets

Participating Departments

    Public Works

contacts

​Stephen Day, P.E.
Project Engineer
Phone: 360-778-7944
Public Works Contacts