Status & Project Schedule

March 2018          Ordered playground equipment
April 5 2018          Bid advertised
April 20 2018        Bid opening date, no bids received.
June 2018              Anticipated delivery date of playground equipment
Oct 2018               Negotiated bid
Mid November     Anticipated contruction start time

Neighborhood Meetings

September 17, 2017 (Samish Neighborhood Picnic at Lake Padden)
Samish Neighborhood Meeting - January 2018

Phase 3 Budget & Funding Source

  • Construction Budget: $98,500.00
  • Funding Source: Park Impact Fees

Consultants & Contractor

 City's Project Manager:

  • Jonathan Schilk, RLA

Design Consultants:

  • The Philbin Group, Landscape Architect, Bow, Wa
  • Hererra Environmental, Civil Engineer

 

Reference

 

 

 

Affected Neighborhoods

    Samish

Participating Departments

    Parks and Recreation

contacts

​Jonathan Schilk, RLA

jschilk@cob.org