Aldrich Road Overlay

Project overview:  ES-0551

Overlay of Aldrich from Northwest to Bellingham City limits.   This project will improve the road driving surface.

Potential challenges include traffic at the existing intersections.

Project is funded by the Transportation Benefit District (TBD).

Status - August 2019

Accomplishments:  now under construction through September 2019.

Next Milestone:  Construction complete.

Project details

  • Status: Construction pending
  • Contract awarded: July 15, 2019
  • Contract amount: $1,195,580
  • Contractor: Colacurcio Brothers Construction
  • Completion date:  September 2019
  • Final contract amount:
  • Vicinity Map

Affected Neighborhoods

    Cordata

Participating Departments

    Public Works