2020 TBD Projects and 40th Street Sidewalk

​​Project Overview: ES-0553

This project includes pedestrian and bicycle facility improvements throughout Bellingham including a new sidewalk on the east side of 40th from Ellwood to Fielding and improvements at the Grant/Kentucky intersection. This will improve pedestrian and bicycle access. 

Funded by Street and Transportation Benefit District. ​

Project Status 

Accomplishments: Project kick-off.

Next Milestone: Survey, 60% plan development.

Project Details

  • Status - Design
  • Contract Awarded -
  • Contract Amount  -
  • Contractor - 
  • Vicini​ty Map

Affected Neighborhoods

    City Center; Columbia; King Mountain; Puget; Samish; Sunnyland; York

Participating Departments

    Public Works

contacts

Freeman Anthony

Project Engineer

(360) 778-7924

fanthony@cob.org​