2019 Transportation Benefit District Projects

​Project Overview:  ES-0547

Transportation Benefit District funded pedestrian and bike improvements throughout Bellingham.  The purpose of this project is to improve safety and connectivity for pedestrian and bike travel.  Possible challenges include available City right-of-way and the existing utilties.

Funding will be provided by Transportation Benefit District funds.  

Status - July 2019

Accomplishments:  60% Design complete

Next Milestone:   Complete 90% design and prepare bid documents.

Project Details

  • Status - construction pending
  • Contract Awarded - July 15, 2019
  • Contract Amount - $1,758,244
  • Contractor - Larry Brown Construction
  • Completion Date:  November 2019
  • Vicinity Map

 

Affected Neighborhoods

    City Center; Columbia; Cornwall Park; Happy Valley; Lettered Streets; Puget; Roosevelt; South Hill; Whatcom Falls

Participating Departments

    Public Works

contacts

​Freeman Anthony, P.E.
project manager
Phone:  (360) 778-7924, fanthony@cob.org

 Public Works Contacts