2018 Watermain Replacements

​​Project Overview: EW-0233

Watermain replacement on E. Maplewood Street (6″ cast iron 1926) from Northwest Ave to Meridian Street and Lorraine Ellis Court (4″ cast iron, 1927.)

Funding from City water utility funds.

Status – February 2021

Accomplishment: Certificate of Completion signed on March 4, 2020.

Previous accomplishments:​

  • Advertise for consultant qualifications 
  • Select consultant – Pacific Surveying & Engineering selected to provide professional design services. Consultant agreement executed
  • ​Prepare scope of work and negotiate agreement
  • Submit Inadvertent Discovery Plan
  • Site survey
  • Initiate design
  • Design 30%
  • Evaluate/select design alternatives
  • Submit Design Report to Ecology for review
  • Design 60%​
  • Ecology Design Report acceptance
  • Submittal of permits
  • Submit Department of Archaeology and Historic Preservation (DAHP) cultural resource document
  • Submittal of 90% Plans, Specifications and Estimate
  • Project Advertisement for bids
  • Council award of construction to Dawson Construction
  • Construction start

Next Milestone: 1 Year Warranty Period – ends March 4, 2021.

Project Details

  • Status – Warranty Period
  • Contract awarded – December 10, 2018
  • Contract amount – $1,512,046.65
  • Contractor –  Dawson Construction
  • Completion Date – October 29, 2019
  • Final Contract Amount – $1,548,557.72
  • Vicinity Map
  • What does this s​​take m​ean?

Contacts

​Larry Scholten, P.E.
Project Engineer
Phone:  (360) 778​-7923
Public Work​s Contacts

Participating Departments

Affected Neighborhoods