TBD-Funded Non-motorized Intersection Projects

Vicinity Map

Project Overview

To provide improved safety for pedestrians at key intersections in the City, the Transportation Benefit District board approved funding for improvements at six intersections.

Status - April 2012

Northwest/Alderwood, State/Maple and Illinois/James Accomplishments: Survey and base mapping are complete.
Next Milestones
: Complete 60% design and route internally for comment.

N. Samish at Abbott and Woburn/Rimland Accomplishments: Authorized contract for survey and base mapping.
Next Milestones: Begin design.

Alabama and St. Paul Accomplishments: Construction complete.  Signal energized.
Next Milestones:

Affected Neighborhoods

Sehome
Central Business District
Sunnyland
Birchwood
Barkley
Roosevelt

Project Manager

Shane Oden, P.E.
Project Engineer
Phone: (360) 778-7921
Email Public Works

Project Details

Construction Photographs

Not yet available      