This project is designed to reduce flooding
on Roeder Avenue while providing improved fish pass
age and bicycle and
pedestrian enhancements. The City of Bellingham has joined a local agency
partnership with the Port of Bellingham, Department of Natural Resources,
and the Department of Ecology. The reconstruction of the bridge will
include pedestrian and bicycle improvements while a section of sewer main
will be replaced with a siphon.
Accomplishments: Soils testing complete. Met with consultant on 2/6/12. to discuss phasing plan on final design concepts.
Next Milestones: Proceed with 60 percent design and re-route for internal comment. Complete interlocal agreement with the Port of Bellingham for management of the project.
Columbia
Waterfront District
Shane Oden, P.E. Project Engineer
Renee LaCroix, Environmental Coordinator
Phone: (360) 778-7900
Email Public Works