Project Overview: ES-0360

Pre-construction PhotoThis project involves construction of a multimodal roundabout at the intersection of Northwest Avenue and McLeod Road to add bicycle and pedestrian safety as well as accommodate motor vehicle traffic circulation.  This is part of the Safe Routes to School project that will teach students to use the intersection to cross Northwest when walking to Birchwood Elementary or Shuksan Middle schools.

The project includes curb, gutter and sidewalk on the north side of McLeod Road between Northwest and West Rusley Drive.

Status - April 2013

Accomplishments:   Curb and gutter for splitter islands, truck aprons and center island installed. Sidewalk has been poured. Sound barrier wall complete.

Next Milestones: Finish pouring truck aprons and splitter islands. Establish final road grade and pave.

Affected Neighborhoods

Birchwood, Meridian, Guide Meridian

Project Manager

Shane Oden. P.E.
Project Engineer
Phone: (360) 778-7900
Email Public Works

Project Details

Construction Photographs

No photos available