The Britton Road stormwater treatment pond conversion project will increase stormwater treatment for phosphorus and other pollutants. Reducing phosphorus entering the lake remains a high priority for maintaining lake water quality.
Accomplishments: Project is substantially complete.
Final inspection help 11-4-10.
Next Milestones: Punch list and closeout.
Silver Beach
Freeman Anthony, P.E.
Project Engineer
Phone: (360) 778-7900
Email Public Works