Project Overview: ES-0414

Hannegan Road PreconstructionThis project consists of pavement preservation and resurfacing Bakerview Road from Deemer to Hannegan Road and Hannegan Road south to Sunset Drive.  The project will include pavement repair, leveling the pavement surface, and resurfacing with asphalt. Existing ADA ramps, drainage and guardrail will be modified to meet current standards. The City is a recipient of "second tier" American Recovery and Reinvestment Act (ARRA) funds for this project. This work will be closely coordinated with the annual overlay program to be advertised later this year.

Status - October 2010

Accomplishments:   Final paving work complete and project is substantially complete. Final inspection held on 9/8/10. Punch list completed.

Next Milestones
:  Document review with WSDOT scheduled for 10/14.

Affected Neighborhoods

Mt. Baker

Project Manager

Dave Mohler, PE
Project Engineer
Phone: (360) 778-7900
Email Public Works

Project Details

Construction Photographs

Digging out failed pavement   Completed dig-out of failed pavement

    