Birchwood Neighborhood Pedestrian Improvements

Birchwood Neighborhood Pedestrian Improvements

Project Overview: ES-0420

Birchwood Neighborhood Pedestrian Improvements - Pre-ConstructionWorking with the Birchwood Safe Route to School team, the Birchwood Neighborhood Group, and the Bicycle/Pedestrian Advisory Committee, Public Works staff will identify, design and construct a pedestrian improvement project in the Birchwood Neighborhood. Initially planned for sidewalk on McLeod Road, the project will be coordinated with other safe route to school projects in the area. The purpose of the project is to facilitate safety for children's walking route in area of elementary and middle school.

Status - September 2009

Accomplishments: All improvements completed this month.  Final inspection held on 8/27/2009.

Next Milestones: Project complete

Affected Neighborhoods

Birchwood

Project Manager

Ravyn Whitewolf
Engineering Manager
Phone: (360) 778-7900
Email Public Works

Project Details

Construction Photographs