This
project will be an extension of the existing street to Marine Drive along
Timpson Way. The project is funded with County, State and Private dollars.
The purpose of the project is to divert truck traffic to designated route
from the residential area.
Accomplishments: Received comments from DOE on Revised Voluntary Cleanup Plan (VCP). Reviewed final plans with Whatcom County. Draft bid documents completed for review.
Next Milestones: Complete all NEPA permits. Obtain "letter of opinion" from DOE. Execute memorandum of understanding with State Historic Preservation Office (SHPO) on plan for archeological monitoring during construction. Hold open house.