Northwest Avenue Pedestrian Improvements

Northwest Avenue Pedestrian Improvements

Project Overview: ES-0315

Northwest Ave Pedestrian Improvements Preconstruction PhotoThis project will provide pedestrian and bicycle facilities on Northwest between McLeod and Bakerview Roads to improve pedestrian and bicycle safety and channelization in the area.

Status - July 2010

Accomplishments: Completed installation of retaining wall, street lighting and curb, gutter and sidewalk. excavation. Two-week closure of  I-5 on-ramp followed by a two-week closure of Northwest Avenue allowed roundabout grading and installation. Completed new paving and overlay sections.

Next Milestones: Complete street markings, landscape and restoration.  Hold final inspection.

Affected Neighborhoods

Birchwood
Meridian
Guide Meridian

Project Manager

Mark Handzlik
Engineering Manager
Phone: (360) 778-7922
Email Public Works

Project Details

Construction Photographs

Stormwater Vault Installation  Stormwater Vault Installation 2  Stormwater Vault Installation 3  Stormwater Vault Installation 4  Stormwater Vault Installation   Storm drains   Storm Drain installation   Storm pipe   Roundabout Nears Completion   Roundabout