Northwest Avenue Pedestrian Improvements

Northwest Avenue Pedestrian Improvements

Project Overview: ES-0315

Northwest Ave Pedestrian Improvements Preconstruction PhotoThis project will provide pedestrian and bicycle facilities on Northwest between McLeod and Bakerview Roads to improve pedestrian and bicycle safety and channelization in the area.

Status - January 2010

Accomplishments: Construction of storm improvements complete.  Project is shut down for winter.

Next Milestones: Utilities should begin pole relocation in January.

Affected Neighborhoods

Birchwood
Meridian
Guide Meridian

Project Manager

Ravyn Whitewolf
Engineering Manager
Phone: (360) 778-7900
Email Public Works