2012 Water Main Replacement Program

Vicinity

Project Overview: EW-0186

The 2012 Water Main Replacement project is part of an annual program to replace aging water mains that Sehome pre-constructionare at the end of their lifecycle and require upgrades. The 2012 project will replace water main and portions of the storm sewer on Key Street between Myrtle and Chestnut Street, Liberty Street between Maple Street and the Dead End, and through the Sehome Arboretum between the Sehome Reservoir and Myrtle Street. Most water main replacement will occur within planter strips.

The project area is within Sehome arboretum and and the Sehome Historic District. The proposed alignment of the new water main was chosen to avoid mature trees and existing landscaping which contribute to the character of the community. Trenchless (pipe bursting) methods will be utilized through the arboretum to minimize any disruption to this wild area.

.

Update - April 2013

Accomplishments: Water main and storm sewer improvements installed on Key and Liberty Streets.

Next Milestones: On-going pavement and landscaping restoration .
.

Affected Neighborhoods

Sehome

Project Manager

Craig Mueller. P.E.
Project Engineer
Phone: (360) 778-7922
Email Public Works

Project Details

Construction Photographs

Water main

                                                   

Top of Page ^ Top of page