Woodstock Farm Septic System

Description

A 2010 evaluation of the Woodstock Farm septic system found that the system has failed and needs to be replaced.  A new septic system has been designed that will serve the future needs of the park.

Funding

The anticipated cost of the new septic system is approximately $140,000 and will be partially paid from the land acquisition reimbursement grant from the Washington State Dept. of Natural Resources, which was allocated for Woodstock Farm improvements.

Status

Design Complete 2013.

Construction is currently underway and expected to be complete by November 2014. 

Woodstock Farm is currently closed to all public access in the areas shown on the Woodstock Farm Temporary Access Restriction during Construction map below.

Reference

Top of Page ^ Top of page