Squalicum Creek Park Phase 3 Development

Photographs

Squalicum Creek Park

Description

Phase 3 improvements include a picnic shelter, playgrounds, loop trail, basketball court, off-leash dog park, the lighted softball field, light phase one ball field, restrooms, site grading, parking lot and parking lot lighting, landscape planting, pedestrian amenities and site infrastructure improvements.

Construction Budget & Funding

$4,700,000 in Greenway Levy 3 and $540,000 in Park Impact Fees.

We hope to be awarded a $500,000 State grant in 2013 to supplement the construction budget.

Project Schedule

2011    Completed preliminary Phase 3 scope of work and cost estimate for construction

May 2012    State grant application due

2012    Continue design of Phase 3 improvements

June 2013    Grant award

January 2014    Bid project

April-December 2014    Construction Phase